STORY

Case study: Secure government facility

April 24 2023

Installing replacement doors at a government facility in Felixstowe saw Rhino Site Systems working alongside several sub-contractors that were completing civil works and external painting. With multiple elements of the project ongoing at once, the teams worked in collaboration, over a three-week period, to bring the site up to the appropriate standard. 

 

The background: 

A government facility in Felixstowe required a set of electrically operated doors, as the originals had been in situ since 1999 and needed replacing. Originally manufactured by Rhino Doors, highlighting the exceptional lifespan and quality of the firm’s doors, the client needed the products to be CPNI approved due to the site’s sensitive nature. 

The site is a secure storage location for materials that have been seized by Border Force, HM Revenue and Customs and the National Crime Agency. Rhino Site Systems was appointed to conduct the installation work and bring the site back up to standard. 

 

The challenge: 

The pair of electrically operated doors supplied were CPNI approved, designed specifically to secure the unloading bay for vehicles delivering seized materials. Rhino Site Systems’ installation supervisor had previously worked on the site, as he had been an apprentice at Rhino when the original doors had been installed, demonstrating the longstanding expertise of the field team. 

The installation itself took place over three weeks and saw Rhino Site Systems coordinating its operations with several sub-contractors. With several elements to the project, it required meticulous planning and attention to detail to ensure its timely conclusion for the client. 

The team removed the old doors at both ends of the compound, with 24-hour security in place during the installation. The civil engineering contractor then dug out the old ground rail and prepared the floor for the installation of the new doors, before a separate contractor repainted the frames and canopies. 

The mechanical installation was then completed, along with the electrical installation, before the new ground rails were concreted in. 

 

The result: 

Following completion, a handover meeting was held with the client to evaluate the project. The client stated that the project “couldn’t have gone much better and all parties worked together to ensure that the original timescale was adhered to.” 

Rhino Site Systems not only installed and commissioned the new doors but has now signed a long-term maintenance contract with the client to ensure that the new doors are in operation for as long as the previous ones.

Learn more about our recent projects by reading another of our case studies here.

MORE ARTICLES

June 09 2023

Rhino Site Systems achieves BM TRADA Q-Mark accreditation

Last month, a Rhino Site Systems employee secured BM TRADA Q-Mark accreditation in recognition of the firm’s commitment to correctly installing and maintaining fire doors in accordance with the relevant manufacturer’s guidelines.  BM TRADA, which is part of the Element Group, works with organisations across a range of different industries to certify that materials, products […]

READ MORE

April 24 2023

Case study: Secure government facility

Installing replacement doors at a government facility in Felixstowe saw Rhino Site Systems working alongside several sub-contractors that were completing civil works and external painting. With multiple elements of the project ongoing at once, the teams worked in collaboration, over a three-week period, to bring the site up to the appropriate standard.    The background:  […]

READ MORE